First Aerial Photograph of Respond Housing, Mulhuddart....
The
first aerial photograph of the Respond Housing development at Ladyswell
Road, Mulhuddart shows the almost-complete state of the project.
The project which consists of 272 units, including a Group Home and a Creche, began on 28th February 2006 and is due for completion at the end of July 2008.
Despite being hampered by delays in diverting the lattice of underground and overhead ESB lines on the 16 acre site, MDY Construction have managed to have the entire development four months ahead of schedule.
The housing units vary from three and four-bedroom traditional two-storey buildings to four-storey apartment blocks with KalZip roofing.
The photograph was taken on 21st November by Peter Barrow, Photographer.